Great progress continues to be made on-site at Stadium Point on Units A-D and Units E and F. The external cladding is now complete on each of the units, with concrete floors poured, and mechanical and electrical works underway alongside intumescent painting.
Once these tasks are complete, the Morris Property team will move on to roller shutter doors, curbing, and tarmacking as they move closer to completing Phase 1 of the project at the end of June.