The first phase is certainly starting to look much better now the tarmac roads are being laid.

We now have 50% of the units Under Offer.

All of the frames are now erected and we now just have the brickwork and cladding to complete.

Buildings 5-8 should have the roofs installed and then onto the cladding within the next few weeks.

All being well and Weather permitting the first phase should be nearly finished towards the end of August 2019/ early September. 2019.

We would like to thank you all for all your patience and co-operation during the construction period which is appreciated by the team and Directors at Morris Property.